Quantcast

SW Bluegrass News

Wednesday, December 25, 2024

Main Street Project Set to Begin

5

The Contractor for the Main Street Streetscape project will mobilize  the week of June 27th.  The initial schedule has been provided to the  City by the Contractor with important milestones shown below.

  • 6/27-7/1:  Mobilization and Tree Removal
  • 7/5-8/2:  Sidewalk Replacement on the south side of Main Street between 3rd and 4th moving from west to east
  • 7/29-8/31:  Sidewalk Replacement on the south side of Main Street between 2nd and 3rd moving from west to east
  • 8/26-9/16:  Sidewalk Replacement on the north side of Main Street between 2nd and 3rd moving from east to west
  • 9/9-10/7:  Sidewalk Replacement on the north side of Main Street between 3rd and 4th moving from east to west
  • 10/17-11/11:  Sidewalk Replacement on the east side of Fourth Street north of Main
  • 11/9-12/19:  Sidewalk Replacement on the west side of Fourth Street north of Main
  • 12/19-1/23:  Sidewalk Replacement on the east side of Fourth Street south of Main
Source: https://www.danvilleky.org/CivicAlerts.aspx?AID=80

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS